Don't forget you can CLICK on a photo to view a larger image.
27th - 31st December 2005 - Work starts at last! return to Latest News
The collapsed roof was removed and the Upright Shaft salvaged. Next to go was the debris on
the floor, which consisted of a mixture of old tyres; rotting timber; polythene bags, and earth.
This was all removed down to the level of the top of the sleeper walls; two walls that divide the
base and originally supported the floor joists. Finally the elder tree was dug out; this was about
twenty feet high, but fortunately the roots were fairly shallow.